Changes for page R20 Docker - Double Lane

Last modified by Erik Bakker on 2026/02/10 10:51

From version 26.1
edited by Erik Bakker
on 2025/06/30 09:51
Change comment: There is no comment for this version
To version 31.1
edited by Erik Bakker
on 2026/02/10 10:43
Change comment: There is no comment for this version

Summary

Details

Page properties
Title
... ... @@ -1,1 +1,1 @@
1 -R17 Docker - Double Lane
1 +R20 Docker - Double Lane
Content
... ... @@ -1,17 +1,52 @@
1 -**Service affecting** final template to use the R16 double lane release.
1 +=== Intermediate Template - Release Notes ===
2 2  
3 +**Non-service affecting** intermediate template to use the R20 double lane release. This is the first of two steps for your upgrade to the new R20 template.
4 +
3 3  **Process**
4 -o use the new R17 template on your environment, we replace all connections to activate the new configuration. This update is service affecting and aims to enable data traffic via our new carwash.
6 +To use the new R20 release of our cloud template we upgrade in two steps, with only the second step being service affecting. Below is the first step.
5 5  
6 6  **Overview**
7 -* New connections to a **new** carwash.
9 +* Security improvements to the eMagiz infrastructure
10 +* Update Ubuntu version
11 +* Update Docker version
12 +* Update control agent version
13 +* Update Authorization Server (if applicable)
8 8  
9 9  **Update Steps**
10 -* Use the final template (non service affecting)(duration: < 10 minutes)
11 -** This step will replace all connections.
16 +* Use this intermediate R20 template (non-service affecting)(duration: < 15 minutes)
17 +** This step will upgrade the backup machines hosted in the second Availability Zone in your cloudslot.
18 +** The network drive containing the Artemis queue store and your Elastic IPs will remain.
19 +** The runtimes on the machines will be restored using the active release in the eMagiz portal
12 12  
13 -* User actions after applying the final template:
14 -** Check if all runtimes are up via the runtime overview or Deploy Architecture
15 -** Check if all runtimes have been installed according to the active release
16 -** Check if messages pass through the bus by verifying a critical message flow in external systems
21 +User actions after applying the intermediate template:
22 +Check if all ".02" runtimes are reachable by the runtime dashboard
23 +Check if all flows have been installed according to the active release
24 +Check if messages pass through the bus by verifying a critical message flow in external systems
17 17  
26 +**Remarks**
27 +
28 +To allow the user to have more control of the upgrade process we now allow to upgrade to the intermediate template as a seperate step. This gives you the option to wait longer before updating the **service affecting** final template. In this time you can do additional verifications on your model.
29 +
30 +=== Final Template - Release Notes ===
31 +
32 +**Service affecting** final template to use the R20 double lane release.
33 +
34 +**Process**
35 +To use the new R20 release of our cloud template we upgrade in two steps, with only the second step being service affecting. Below is the remaining step.
36 +
37 +**Overview**
38 +* Security improvements to the eMagiz infrastructure
39 +* Update Ubuntu version
40 +* Update Docker version
41 +* Update control agent version
42 +* Update Authorization Server (if applicable)
43 +
44 +**Update Steps**
45 +* Use the final R20 template (non-service affecting)(duration: < 15 minutes)
46 +** This step will upgrade the primary machines in the first Availability Zone in your cloudslot.
47 +** The runtimes on the machines will be restored using the active release in the eMagiz portal.
48 +
49 +User actions after applying the final template:
50 +Check if all ".01" runtimes are reachable by the runtime dashboard
51 +Check if all flows have been installed according to the active release
52 +Check if messages pass through the bus by verifying a critical message flow in external systems